Quantity of Cement and Sand Calculation
Quantity
of cement mortar is required for rate analysis of brickwork and plaster or
estimation of masonry work for a building or structure. Cement mortar is used
in various proportions, i.e. 1:1, 1:2, 1:3, 1:4, 1:6, 1:8 etc.
Calculation of quantity of cement mortar in brickwork and plaster:
For the calculation of cement mortar, let
us assume that we use 1m3 of cement
mortar. Procedure for calculation is:
1. Calculate the dry volume of materials
required for 1m3 cement mortar. Considering
voids in sands, we assume that materials consists of 60% voids. That is, for 1m3 of wet cement mortar, 1.6m3 of materials are required.
2. Now
we calculate the volume of materials used in cement mortar based on its
proportions.
Let’s say, the proportion of cement and sand in mortar is 1:X, where X is the
volume of sand required.